Investment
Capital projects
A JOD 220 million portfolio strengthening supply, treatment and metering through 2028.
Zara Ma'in transmission reinforcement
Budget: JOD 48.5M · Target: Q2 2027
In execution
Progress72%
Amman wastewater network expansion
Budget: JOD 112M · Target: Q4 2028
In execution
Progress41%
Smart metering rollout – phase 3
Budget: JOD 26M · Target: Q1 2027
In execution
Progress58%
Ain Ghazal treatment plant upgrade
Budget: JOD 33.2M · Target: Q1 2026
Completed
Progress100%