Investment

Capital projects

A JOD 220 million portfolio strengthening supply, treatment and metering through 2028.

Zara Ma'in transmission reinforcement

Budget: JOD 48.5M · Target: Q2 2027

In execution
Progress72%

Amman wastewater network expansion

Budget: JOD 112M · Target: Q4 2028

In execution
Progress41%

Smart metering rollout – phase 3

Budget: JOD 26M · Target: Q1 2027

In execution
Progress58%

Ain Ghazal treatment plant upgrade

Budget: JOD 33.2M · Target: Q1 2026

Completed
Progress100%